Dahej Expansion Phase-III, LNG Storage Tanks


Dahej Expansion Phase-III, LNG Storage Tanks
Dahej Expansion Phase-III, LNG Storage Tanks
Dahej Expansion Phase-III, LNG Storage Tanks

Tanks

  • Location: Dahej, Gujarat
  • Client: Afcons Infrastructure Ltd.
  • Awarded: 2010
  • Status: Completed

Scope of Work

  • Supply and installation of Horizontal and Vertical sheathing, strand threading, stressing and grouting.

Petrnont LNG Limited had set up South East Asia's first LNG Receiving and Regasification Terminal with an original nameplate capacity of 5 MMTPA at Dahej, Gujarat using Freyssinet Prestressing C-Range Anchorage system.

FMI was involved in construction of two numbers of LNG stone tanks in Dahej LNG phase III A in for Petronet LNG Limited.

Horizontal tendon length was 148 m and Vertical tendon length was 40.3 m. 19C15 system applied in Both Vertical and Horizontal tendons. Strand specification 15.7 mm (EN 10138 tensile strength 1860 mpa).Total tonnage of the strands is 1470 ton.